2 to 1 Vote Approves New Roof for Old Firehouse

News, Police & Government
2019 millage rate

Blue Ridge, Ga – Commissioners approved reroofing of the old firehouse located next to the courthouse in a two to one vote with Post Two Commissioner Glenn Patterson dissenting.

Chairman Stan Helton brought up the need for a new roof on the old firehouse during the last meeting. The committee tabled the issue until the July 9 meeting.

“It is leaking. It’s not in danger of falling in right now, but another hard winter over there could really take us backward a long ways,” commented Helton.

Two quotes came back for the roof, one from Steve Stacy Roofing at $30,723.16 and from J&D Construction and Excavating at $28,147.

“J&D Construction did our old jail that houses our maintenance office,” state Helton, “As far as I can tell that work has turned out fine.”

Patterson visited with the old fire station and expressed concern in the state of the entire building.

“It’s in pretty bad shape,” commented Patterson, “My concern is if that roofing is going to do the job. We might have some drainage issues as well. I know that these two quotes checked the roof out and I guess we’ll get the roof on it and see.”

Patterson wanted to add a new roof, but the drainage and potential mold issues also merited consideration. He was unsure how long offices could remain usable in the current state.

“We don’t want any danger to our employees,” said Patterson.

Patterson brought up multiple issues with the old fire station.

Post one Commissioner Earl Johnson agreed that the building needs a new roof and the county should start there as it’s the most pressing issue.

“The concern I would have with the building. We start with the roof, stop all the leaks. There’s no telling how old that roofing is and how long it’s been on there,” commented Johnson.

J&D Construction will remove the entire roof and replace with new shingles and materials. Johnson recommended using J&D for that reason and because Stacy Roofing’s bid accounted for $65 per sheet of plywood fixes. Stacy’s estimate could result in extra charges once the project begins.

“When I parked this afternoon, I noticed all the fascia boards and most of them were rotten, and [J&D]’s quote states that they’re going to replace all the fascia boards and replace with new,” said Johnson, “Not only just price but the amount of work that’s going to be done. It looks like a significant amount more with J&D.”

Helton responded to Patterson’s concerns about the long-term usability of the firehouse. The building needs to be available for office space for the county, and other entities might need it in the future. With rental rates increasing, more departments might need to move into the old fire station.

“It is a county asset; there’s value to it. If we take care of it like we should do our county assets, we should make some usable space available. If we do the roof, which I really believe we should do this year, and we can discuss at a later time what we should do next,” explained Helton.

Patterson asked to address the baseboards, flooring, and doors after installation of the new roof.

Johnson added that he wanted to clarify with J&D about the gutters and if they accounted for gutters in the initial scope of work.
Helton confirmed neither company included guttering in the initial quote. Patterson asked to include it in the project costs because it’s necessary for a new roof.

“We may have some leverage if we wait with the guttering on the drainage issue,” said Patterson.

“I don’t have a problem moving forward with the roof and negotiating the guttering,” stated Johnson.

Helton made a motion to approve the J&D bid for the new firehouse roof, which passed 2 to 1 with Patterson against the decision due to lack of guttering in the initial quote.

Road Detail Update

Director of Public Works Zack Ratcliff approached the board for permission to buy a 2010 Van 13K to transport the work detail from Blairsville.

“I’ve looked high and low at our dealerships, and a passenger van is really hard to find,” stated Ratcliff, “Lucked up on one at AA Auto Rental, I went up and drove it. $13,000 is the price on it with 100,000 miles on it.”

Colwell Detention Center requires counties to have a way to transport work details back and forth from the facility to the roadside.

“We expected this when we decided to hire them,” said Johnson.

The van will be available on Monday, July 22, after it is fitted to meet all detention center requirements.
The board unanimously approved the purchase.

Leave a comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

FetchYourNews.com - Dedicated to serve the needs of the community. Provide a source of real news-Dependable Information-Central to the growth and success of our Communities. Strive to encourage, uplift, warn, entertain, & enlighten our readers/viewers- Honest-Reliable-Informative.

News - Videos - TV - Marketing - Website Design - Commercial Production - Consultation

Search

FetchYourNews.com - Citizen Journalists - A place to share “Your” work. Send us “Your” information or tips - 706.276.NEWs (6397) 706.889.9700 chief@FetchYourNews.com

Back to Top